Road Construction Delay Risk Identification Based On The Relative Importance Index Method
(1) Department of Civil Engineering, Faculty of Engineering, University of Riau, Pekanbaru, Riau.
(2) Department of Civil Engineering, Faculty of Engineering, University of Riau, Pekanbaru, Riau.
(3) Department of Civil Engineering, Faculty of Engineering, University of Riau, Pekanbaru, Riau.
(*) Corresponding Author
DOI: https://doi.org/10.25077/jrs.20.2.83-96.2024
Copyright (c) 2024 Heldifha Fadlansyah, Ari Sandhyavitri, Rian Tri Komara Iriana
Abstract
The Widening Project to Add Lanes to the Siak IV Pekanbaru Access Road is one of the road construction projects that experienced a delay of 27.791% of the planned schedule. The delay requires risk identification and assessment as an initial form of risk management. This study aims to identify the causal factors of the risk of delays during the construction period by using one of the risk identification methods, namely the Relative Importance Index (RII) method with a Likert Scale, the influence from no effect or 1 to very influential or 5. Out of 63 risk variables delays obtained 11 valid risks by the validity test with the Item-Level Content Validity Index (I-CVI). Therefore, using the RII method, a list of risks from the highest impact to project delay was obtained which was equipment with a value of 1.00 and the last was rain with a value of 0.25. To prove the risk factors, The Critical Path Method (CPM) was then applied, revealing 26 activities categorized as critical paths in 9 main works of the project. In conclusion, the risks were proved which caused the project delay and impacted the critical path in progress of the project.
Keywords
Full Text:
PDFReferences
Al-Mohammad, M., & Bin Jamaludin, O. (2020). Review of Causes of Delay in Construction Projects. Journal of Computational and Theoretical Nanoscience, 17(2–3), 715–728. https://doi.org/10.1166/jctn.2020.8710
Badan Pusat Statistik. (2023). Pertumbuhan Ekonomi Indonesia Triwulan IV-2022. Badan Pusat Statistik, 17/02/Th. XXIV, 1–12. https://www.bps.go.id/pressrelease/2020/02/05/1755/ekonomi-indonesia-2019-tumbuh-5-02-persen.html
Damanik, M., Sandhyavitri, A., Fauzi, M., & Faktor-Faktor Yang Mempengaruhi Keterlambatan Pembangunan Kawasan Perumahan Studi Kasus Proyek Perumahan di Pulau Padang, A. (2020). Jurnal Aptek Analisis Faktor-Faktor Yang Mempengaruhi Keterlambatan Pembangunan Kawasan Perumahan (Studi Kasus Proyek Perumahan Di Pulau Padang, Riau). Jurnal APTEK, 12(2), 81–88. http://journal.upp.ac.id/index.php/aptek
Davis, L. L. (1992). Instrument review: Getting the most from a panel of experts. Applied Nursing Research, 5(4), 194-197. https://doi.org/10.1016/S0897-1897(05)80008-4
Faisal, M., & Tenrisukki Tenriajeng, A. (2021). Analisis Risiko Pada Tahap Pelaksanaan Konstruksi Jalan Tol. 4(1), 33–42.
Freeman, R. E. (1984). Strategic Management: A Stakeholder Approach. Pitman.
Garg, R., & Rawat, S. (2021). Analysis of Risk Assessment in Highway Projects Using Importance Index. IOP Conference Series: Materials Science and Engineering, 1116(1), 012157. https://doi.org/10.1088/1757-899x/1116/1/012157
Genc, O. (2021). Identifying Principal Risk Factors of Turkish Construction Sector According to Their Probability of Occurrences : A Relative Importance Index ( RII ) and Exploratory Factor Analysis (... July. https://doi.org/10.1080/15623599.2021.1946901
Institute, P. M. (2017). A Guide to the Project Management Body Of Knowledge (6th ed.). Project Management Institute, Inc.
Kementerian Pekerjaan Umum dan Perumahan Rakyat Republik Indonesia. (2022). Informasi Statistik Infrastruktur.
Levin, R. I., & Kirkpatrick, C. A. (1982). Perencanaan dan Pengendalian dengan PERT dan CPM: Teknik Penilaian dan Peninjauan Program dan Metode Jalur Kritis. Balai Aksara.
Lynn, M. (1986) Determination and Quantification of Content Validity Index. Nursing Research, 35, 382-386.
https://doi.org/10.1097/00006199-198611000-00017
Mahamid, I., Bruland, A., & Dmaidi, N. (2013). Causes of delay in road construction projects in Malawi. Journal of the South African Institution of Civil Engineering, 55(3), 79–85. https://doi.org/10.1061/(ASCE)ME.1943-5479.0000096
Mahamid, I., & Laissy, M. (2019). Time Overrun in Construction of Road Projects in Developing Countries: Saudi Arabia as a Case Study. Risk Management in Construction Projects: Case Studies View Project Construction Management in Palestine View Project International Journal of Engineering and Information Systems (IJEAIS), 3(6), 18–23. https://www.researchgate.net/publication/355476624
Polit, D.F., Beck, C.T. and Owen, S.V. (2007) Is the CVI an Acceptable Indicator of Content Validity? Appraisal and Recommendations. Research in Nursing & Health, 30, 459-467. http://dx.doi.org/10.1002/nur.20199
Polit, D.E. and Beck, C.T. (2006) Essentials of Nursing Research. 6th Edition, Lippincott Williams & Wilkins, Philadelphia.
Popham, W. J. (1978). As always, provocative. Journal of Educational Measurement, 15(4), 297–300. https://doi.org/10.1111/j.1745-3984.1978.tb00077.x
Rooshdi, R. R. R. M., Majid, M. Z. A., Sahamir, S. R., & Ismail, N. A. A. (2018). Relative importance index of sustainable design and construction activities criteria for green highway. Chemical Engineering Transactions, 63(2007), 151–156. https://doi.org/10.3303/CET1863026
Sandhyavitri, A. (2022). Stochastic analyses for managing risk of delay in Duri oil construction projects, Indonesia. International Journal of Construction Management, 22(4), 711–731. https://doi.org/10.1080/15623599.2019.1644762
Surveyor, A. (1999). Standards association of australia. Australian Surveyor, 4(7), 426. https://doi.org/10.1080/00050326.1933.10436323
Tobing, Y. O. L., Sari, D. P., & Wicaksono, P. A. (2019). Analisis Risiko Proyek Konstruksi Dengan Importance Index dan Bow Tie Analysis. Industrial Engineering Online Journal, 7(4), 2018.
Vasishta, N., Chandra, D. S., & Asadi, S. S. (2018). Analysis of risk assessment in construction of highway projects using relative importance index method. International Journal of Mechanical Engineering and Technology, 9(3), 1–6.
Vishwakarma, A., Thakur, A., Singh, S., & Salunkhe, A. (2016). Risk Assessment in Construction of Highway Project. International Journal of Engineering Research And, V5(02), 637–641. https://doi.org/10.17577/ijertv5is020515
Waltz, C.F., Strickland, O. and Lenz, E.R. (2010). Measurement in nursing and health research. Springer Publishing Company, New York.